Opening or reworking a restaurant in Georgia means answering to four or five different offices. Describe the job on Commercial Kitchen Connect and it goes to general contractors that work near your address. You pick one and deal with it directly.
What a general contractor takes on
On a kitchen project the contractor ties the trades together, files permit applications and books inspections. For a restaurant that usually covers the hood and fan, the plumbing and grease line, fire protection and the finish work. The health office wants to see the menu, the floor plan, the mechanical drawings and the fixed equipment, so have them ready.
The health office sees plans first
DPH Rule 511-6-1-.02 requires a new or heavily remodeled food service to submit plans to the county health authority at least 14 business days before construction begins. The review period starts before anyone touches a wall. Fulton County's authority is the Board of Health. In Gwinnett, Newton and Rockdale counties it is GNR Health.
A permit comes after a complete application, the fee, approved plans and a preoperational inspection. It does not transfer to a new owner, so a restaurant that is sold needs a fresh application.
Get prices for this job. Send one request and pick how many local companies quote it.
Get quotesOther permits sit outside the health permit
Fulton County's brochure describes the food permit as the first of many steps. Business licensing, a liquor license for a bar and zoning approval each run on their own track. Building, mechanical and plumbing work needs separate permits from the city or county.
The state's minimum codes now include the 2024 International Mechanical Code with Georgia amendments, as of January 1, 2026. The 2024 building and plumbing codes apply too. Your local permit office is the one that applies them to your job.
Two metro offices, two ways to apply
- Atlanta: applicants upload PDF files to the city's online permitting portal. Staff want the physical state contractor license card. A printout from the Secretary of State will not stand in for it.
- Gwinnett County: Planning and Development covers commercial construction and tenant certificates of occupancy. Applications and inspection requests run through the ZIP Portal.
How the steps tend to line up
Each office wants to see approvals from the others, so the sequence counts for more than the speed of any one step. Health plan review is normally booked first. Hood and suppression plans go to the office your fire marshal names. A sewer utility may ask for grease trap sizing and the sewer connection before it clears the plumbing permit. Inspections close out the job: the health authority does construction inspections and then the preoperational inspection before issuing the permit, while the building office checks the permitted work.
In Atlanta, stamped plans stay at the site for inspectors to see. A request in before 3:00 p.m. gets inspected within two business days.
What to ask a contractor
- Has it pulled permits in your city or county?
- Who sends the plans to the health office, and who handles its questions?
- Do the hood and suppression plans go to the state or to the local fire marshal?
- Will the sewer utility want trap sizing before the plumbing permit?
- Who will be present at each inspection?
The fire marshal can tell you where fire plans go, since it varies with the building.
Questions
How far ahead of construction do plans go to the health office?
Plans for a new or extensively remodeled food service are due at least 14 business days before the work begins, under DPH Rule 511-6-1-.02.
Does a remodel need health office plan review?
A large remodel does. The county health authority reviews the plans ahead of the work and then inspects the finished space.
Is the health permit the only approval a Georgia restaurant needs?
No. Business licensing, zoning and building permits are separate steps, and a county brochure calls the food permit only the first of many.
Will a permit office ask for my contractor license card?
Atlanta asks for the physical state-issued contractor license card. Check with your own permit office to learn which license it requires.